Join us in the exchange of information and best practices regarding design, build and maintenance

Case Study – Saving Data Center Energy & IT Cooling Capacity

Written by Chris Parlee | Jun 2, 2011

 

The Hanover Insurance Group was looking to improve their data center’s cooling efficiency, as well as the current system’s capacity – while allowing for increased IT (Information Technology) equipment densities within their data center at their headquarters in Worcester, MA.


EEC, working closely with The Hanover, recommended a unique solution that could not only save energy and eliminate hot spots, but also maximize IT cooling capacity in the data center. The system featured a series of networked underfloor and overhead air movers, server rack and Computer Room Air Conditioner (CRAC) temperature sensors, sensor hubs, CRAC controllers and Environmental Management Software.

The Challenge:

  • Integrate new energy-efficiency technology within the data center, without affecting day-to-day operations
  • Eliminate all the data center’s hot spots
  • Achieve all this without making major changes to the existing data center infrastructure
  • Meet the Company’s less-than-24-months economic payback criteria

Summary of Project:

  • Cost of project: $144,000.00
  • Estimated annual savings: 600,000 kWh
  • Utility incentive: $21,500.00
  • Company payback: 16 months (with rebate)

Benefits:

  • Five out of 13 CRAC units were placed into hot-standby, and energy usage for cooling the data center was reduced by 27%
  • Increased cooling redundancy
  • Increased IT load capacity by 70kW
  • IT equipment is thermally safe
  • 24x7 monitoring allowing for automated CRAC unit response
  • Energy incentive from the National Grid Commercial Energy Efficiency Program